The Whitsunday Regional Council undertook new works to provide a lined landfill cell as current infrastructure on the Bowen Landfill site is un-lined. The Bowen Landfill is located on Peter Delemonthe Road (Bowen Development Road) approximately 14km from Bowen CBD, and is on a designated B-Double Route.

Scope of Works

  • Earthworks and Profiling of sites formation.
  • Supply of liner and GCL & welding liner
  • Supply & placement of cushion geotextile
  • Supply & install leachate collection system including a drainage layer and primary pipes.
  • Supply & install a leachate transfer system and dedicated storage pond with similar construction to the main cell works

Implementation of Landfill Design

The sequencing of the works involved the planning, design and construction of:

  • Site preparation for Landfill Lining works
  • Leachate drainage and collection system.
  • Leachate transfer and storage.

Importation of material

  • During the construction of the landfill The Mendi Group haulage fleet delivered over 185,000T of material to the site . At times there was over 100 loads a day being delivered